How Retainage Reduction Works at 50% Completion (10% to 5% Step-Down Guide)
Many commercial subcontracts drop retainage from 10% to 5% once the project reaches 50% completion. Learn the two accounting methods GCs use so your Line 5 math is accepted.
Key Takeaway: Always confirm whether your subcontract specifies a '5% across-the-board retroactive reduction' (releasing half of prior retainage) or '0% retainage on the remaining 50% of work' (holding a fixed 5% cap).
Method A vs. Method B Retainage Step-Down
- Method A (Retroactive Drop to 5%): Change Completed Retainage % from 10% to 5% on G702 Line 5a. Because Line 5a calculates cumulatively on Cols D + E, Line 6 rises and releases half of previously withheld retainage into Current Payment Due.
- Method B (Cap at 5% of Contract Sum / Zero Additional Retainage): Retainage stays frozen at 5% of total contract value (10% of the first 50% completed), and 0% is withheld on the second half of work—resulting in 5% effective retainage at 100% completion.
Build & Roll Forward Your Next Pay App in 60 Seconds
Free G702/G703-compatible PDF/CSV export, AI Bid-to-SOV extraction & 12-state lien waivers.
Launch PayAppKit Studio →
Disclaimer: PayAppKit is independent progress-billing software and is not affiliated with or endorsed by the American Institute of Architects (AIA). Lien waiver references are provided for educational and administrative convenience and do not constitute legal advice.