G702 & G703 Progress Pay Application Line-by-Line Accounting Guide
Master every line on a G702-compatible Cover Sheet (Lines 1–9) and G703 Continuation Sheet (Columns A–I) so General Contractors approve your progress billing on the first submission.
Key Takeaway: Golden Reconciliation Rule: The Grand Total of G703 Column C (Scheduled Value) must ALWAYS equal G702 Line 3 (Contract Sum to Date = Original Contract Sum ± Approved Change Orders).
G702 Cover Sheet: Lines 1 Through 9 Explained
- Line 1 — Original Contract Sum: Your base executed subcontract value before any approved change orders.
- Line 2 — Net Change by Change Orders: Total approved Additions minus approved Deductions across prior months and the current billing cycle.
- Line 3 — Contract Sum to Date: Line 1 plus or minus Line 2. This figure must match the bottom total of Column C on your G703 Continuation Sheet.
- Line 4 — Total Completed & Stored to Date: Copies directly from the Grand Total of G703 Column G (Previous Work + This Period + Stored Materials).
- Line 5 — Retainage (5a & 5b): Line 5a multiplies Completed Work (Cols D + E) by your retainage rate (typically 10% or 5%); Line 5b applies stored-material retainage to Column F.
- Line 6 — Total Earned Less Retainage: Line 4 minus Total Retainage (Line 5a + 5b). Remember this number—it becomes next month's Line 7!
- Line 7 — Less Previous Certificates for Payment: Equals Line 6 from the immediately preceding Pay Application.
- Line 8 — Current Payment Due: Line 6 minus Line 7. This is the exact check amount you are invoicing this month.
- Line 9 — Balance to Finish, Including Retainage: Line 3 minus Line 6.
G703 Continuation Sheet: Columns A Through I
- Col A & B (Item # and Description of Work): Organize by CSI MasterFormat scope milestones (Mobilization, Submittals, Rough-In, Gear/Materials, Trim, Commissioning).
- Col C (Scheduled Value): Contract dollar allocation per line item, including separate lines for approved Change Orders.
- Col D (From Previous Application): Cumulative installed work billed on prior apps (previous Col D + previous Col E).
- Col E (This Period): New work installed during the current billing cycle.
- Col F (Materials Presently Stored): Purchased materials stored safely on site or in a bonded warehouse (never double-count inside Col D or E).
- Col G (Total Completed & Stored to Date): D + E + F. Divided by Col C yields your % Complete.
- Col H (Balance to Finish): C minus G. Must never go negative on positive contract lines.
- Col I (Retainage): Variable or global retainage withheld per line.
Build & Roll Forward Your Next Pay App in 60 Seconds
Free G702/G703-compatible PDF/CSV export, AI Bid-to-SOV extraction & 12-state lien waivers.