Construction Retainage Calculator & G702 Line 5 Accounting Guide

Calculate 10% and 5% retainage accurately across Completed Work (Line 5a) and Stored Materials (Line 5b), plus per-line variable retainage for bonds and mobilization.

Key Takeaway: Retainage is calculated cumulatively on Total Completed to Date (Cols D + E) and Stored Materials (Col F)—NOT just on 'This Period'!

Why Cumulative Retainage Math Matters

When to Use Per-Line Retainage %

Build & Roll Forward Your Next Pay App in 60 Seconds Free G702/G703-compatible PDF/CSV export, AI Bid-to-SOV extraction & 12-state lien waivers.
Launch PayAppKit Studio →