Construction Retainage Calculator & G702 Line 5 Accounting Guide
Calculate 10% and 5% retainage accurately across Completed Work (Line 5a) and Stored Materials (Line 5b), plus per-line variable retainage for bonds and mobilization.
Key Takeaway: Retainage is calculated cumulatively on Total Completed to Date (Cols D + E) and Stored Materials (Col F)—NOT just on 'This Period'!
Why Cumulative Retainage Math Matters
- On G702, Line 5a equals Retainage % × (Total Col D + Total Col E). Line 5b equals Stored Retainage % × Total Col F.
- Because Line 7 subtracts prior Total Earned Less Retainage (prior Line 6), calculating retainage cumulatively automatically nets out the exact current-period retainage deduction—and makes mid-project retainage step-downs (10% to 5%) work cleanly!
When to Use Per-Line Retainage %
- Some General Contractors waive retainage on Performance Bonds, Insurance, or Permits (0% retainage) while holding 10% on trade labor and materials.
- Enable 'Per-Line Retainage %' in PayAppKit to set 0% on Line 001 (Bond/Permits) and 10% on installation lines while keeping G702 Line 5a reconciled to the penny.
Build & Roll Forward Your Next Pay App in 60 Seconds
Free G702/G703-compatible PDF/CSV export, AI Bid-to-SOV extraction & 12-state lien waivers.
Launch PayAppKit Studio →
Disclaimer: PayAppKit is independent progress-billing software and is not affiliated with or endorsed by the American Institute of Architects (AIA). Lien waiver references are provided for educational and administrative convenience and do not constitute legal advice.