How to Show Approved & Deductive Change Orders on G702 & G703 Pay Apps
Avoid unbalanced pay applications when adding approved Change Orders or credit deductions. Learn how G702 Line 2, the Change Order Summary Box, and G703 rows connect.
Key Takeaway: Never bill an UNAPPROVED Change Order Request (COR) on your G702 pay app unless the GC authorizes a pencil-copy placeholder—unapproved COs trigger automatic rejection.
Keeping G702 Line 2 and G703 Column C Balanced
- Every executed Change Order must appear in TWO places: (1) the G702 Change Order Summary Box (which feeds Line 2 Net Change by Change Orders), and (2) as its own dedicated line item at the bottom of your G703 Schedule of Values.
- For deductive credits (negative Change Orders), enter the credit under Deductions on G702 and as a negative Scheduled Value line on G703 so Line 3 and Col C Total remain equal.
Instant Reconciliation with PayAppKit
- PayAppKit's live Reconciliation Check alerts you immediately if Approved Change Orders don't match your G703 CO lines, and offers a 1-click 'Sync Approved COs to G703' button.
Build & Roll Forward Your Next Pay App in 60 Seconds
Free G702/G703-compatible PDF/CSV export, AI Bid-to-SOV extraction & 12-state lien waivers.
Launch PayAppKit Studio →
Disclaimer: PayAppKit is independent progress-billing software and is not affiliated with or endorsed by the American Institute of Architects (AIA). Lien waiver references are provided for educational and administrative convenience and do not constitute legal advice.